Closeout Desk Closeout Desk Get Started
CSI Division 25, MasterFormat

Division 25 Integrated Automation Closeout Documentation Requirements

Integrated automation closeout is reviewed by the commissioning authority, the owner's facilities and energy team, and the mechanical engineer, because the building automation system is what they will operate every day. A package missing as-built sequences or controller backups leaves the owner unable to run or modify the system they paid for.

Quick Reference: What You Need to Collect

Every document required in a Division 25 Integrated Automation closeout package, including who provides it and when it applies.

Document Applies
As-Built Sequences of Operation (Final) Always
BAS Point-to-Point Checkout Reports Always
Functional Performance Test (FPT) Records Always
Control System Commissioning Report If applicable
BAS O&M Manual (System-Specific) Always
Controller & Graphics Program Backups Always
Network Topology & Riser Diagrams (As-Built) Always
BAS Software License Certificates Always
Operator Training Records Always

Division 25 is the connective tissue of a modern building. The building automation system ties HVAC, lighting, metering, and often Division 21 and 28 life-safety points into one supervisory network, so its closeout documentation comes almost entirely from a single source: the controls contractor or system integrator. That concentration sounds like it should make collection simple. In practice it does the opposite, because the integrator is usually the last trade to finish, completing programming, graphics, and functional testing after every other system has been energized and balanced.

The documentation gap on this division is rarely about missing binders. It is about version drift. Sequences get tuned during commissioning, set points are adjusted after the TAB contractor balances the air and water systems, and controller code is patched right up to the acceptance test. The as-built record that lands in the closeout package frequently reflects the submittal version, not the logic actually running in the field. Add the items almost no one asks for, namely the controller and graphics database backups, the BACnet or LON device address tables, and the software license certificates, and you have a package that looks complete on a table of contents but cannot actually rebuild the system.

What is at stake here is operational control, not just retainage. When the warranty expires and a future integrator (sometimes a different manufacturer's dealer) is hired to expand the system, they need the program backups and network documentation to touch it without starting from scratch. Owners and their commissioning authorities know this, which is why BAS closeout is gated tightly: many specifications tie the integrator's final payment and the start of the warranty period to an approved commissioning report, accepted record drawings, and delivered training. Hand over an incomplete package and you may find the warranty clock does not start and the administrative access credentials never transfer.

Required Deliverables: Detailed

What each document is, why it's required, and what to watch for. Written for the GC PM collecting documents from multiple subs and engineers.

As-Built Sequences of Operation (Final)

The final sequences must describe the logic as actually programmed and tuned in the controllers at acceptance, including occupied and unoccupied modes, economizer and reset strategies, staging, alarm limits, and safeties. During commissioning, integrators routinely adjust loop tuning, set points, and staging logic, and the original design narrative rarely captures those changes. The owner's facilities staff rely on these sequences daily to diagnose comfort complaints and to understand why the system behaves the way it does.

PM

Require a sequence-by-sequence comparison against the approved submittal. If the integrator hands you the same narrative submitted as a shop drawing, that is the design version, not the as-built.

BAS Point-to-Point Checkout Reports

Point-to-point checkout verifies every physical and virtual point end to end: the field sensor or actuator, the wiring, the I/O termination, and the value displayed at the operator workstation. The report lists each point by controller and object name with its checkout result and any calibration offset. This is the foundational record that the installation is wired, addressed, and calibrated correctly before functional testing begins.

PM

Confirm the point count in the report matches the I/O point list in the approved submittal. A checkout that covers only representative points rather than every point is not complete and is a common shortcut.

Functional Performance Test (FPT) Records and Commissioning Report

Functional performance testing exercises each sequence under simulated and real conditions to confirm the system responds as designed: failure modes, interlocks, staging, setback, and alarm annunciation. On commissioned projects the commissioning authority witnesses these tests and compiles them into a commissioning report with an issues log. Each test record should show the expected result, the observed result, and a pass or fail disposition.

PM

A commissioning report with open issues is not finished. Every line in the issues log should read resolved or formally deferred with written owner acceptance before the report enters the closeout package.

BAS O&M Manual (System-Specific)

The operations and maintenance manual for the automation system covers the supervisory software, controllers, gateways, and field devices actually installed, with model numbers, configuration settings, and maintenance procedures. It should include the point naming convention, the alarm and trend configuration, and instructions for backing up and restoring the database. Generic manufacturer literature pulled from a website does not satisfy this requirement.

Sub

Tie your O&M content to the as-built point list and network diagram. A binder of cut sheets with no system-specific configuration data will be returned.

Controller and Graphics Program Backups

The closeout package must include the actual program and database files: controller logic, the graphics and screens database, the point database, and any custom programming. These backups are what allow a future technician to restore a failed controller or modify the system without rebuilding it from observation. Many owners discover these files were never delivered only when a controller fails out of warranty.

PM

Ask for the editable program files in the manufacturer's native engineering format on owner-controlled media, not just PDF screenshots of the graphics. Confirm the files actually open in the engineering tool.

As-Built Network Topology and Riser Diagrams

As-built network documentation shows the supervisory and field-bus architecture: controller locations, BACnet/IP, MS/TP, and LON segments, device addresses (MAC and instance numbers), gateway locations, IP assignments, and cable routing. This is the map a future integrator needs before touching the system. It must reflect the installed network, including any field changes to addressing or routing made during startup.

PM

Verify device addresses and instance numbers on the diagram against the live device list at the operator workstation. Address tables drift during commissioning when controllers are added, moved, or re-addressed.

Software License Certificates and Administrative Access Credentials

Building automation platforms are licensed software protected by tiered passwords. The closeout package must transfer the software license certificates to the owner along with administrator-level credentials, so the owner is not captive to a single service provider. Without the licenses and admin access, the owner holds a system they cannot fully program or expand, and the proprietary engineering tools may revert to the integrator. This item is frequently overlooked because it has no physical deliverable.

PM

Confirm the license is registered to the owner, not the integrator, and that administrator or operator credentials are formally transferred in writing. View-only access is not ownership.

Governing Standards

The codes and standards that define what's required in a Division 25 Integrated Automation closeout package. Reference these when an owner or architect pushes back.

ANSI/ASHRAE 135 BACnet: A Data Communication Protocol for Building Automation and Control Networks

Defines the BACnet protocol used by most building automation systems. As-built network documentation should identify device and object instances and the protocol versions in use for interoperability.

ASHRAE Guideline 0 The Commissioning Process

Establishes the overall commissioning process and documentation, including functional performance testing and the systems manual that BAS closeout feeds into.

ASHRAE Guideline 1.1 HVAC&R Technical Requirements for the Commissioning Process

Provides the technical commissioning requirements for HVAC controls, including point-to-point checkout, sequence verification, and functional performance testing.

ANSI/ASHRAE 90.1 Energy Standard for Sites and Buildings Except Low-Rise Residential

Mandates direct digital control capabilities, economizer and reset strategies, and controls commissioning that the as-built sequences and FPT records must demonstrate.

ISO 16484 Series Building Automation and Control Systems (BACS)

International standard series covering BACS hardware, software, functions, and the BACnet data communication protocol, sometimes referenced for BAS functional and documentation requirements.

Why Division 25 Packages Get Rejected

These are the specific issues that cause owner rejection, AHJ refusal, or retainage holds. Each one is documented with the root cause and how to prevent it.

Submittal sequences submitted as as-built sequences

This is the most common rejection on Division 25. The integrator tunes loops, changes set points, and revises staging during commissioning, then submits the original shop-drawing narrative as the as-built. Reviewers compare the narrative against the commissioning trend data and find set points and modes that do not match what is actually running.

PM

Have the integrator redline the approved sequence narrative with every change made during startup, or export the sequence logic directly from the controller.

Sub

Keep a running markup of sequence changes during commissioning rather than reconstructing them from memory at the end.

Point-to-point checkout covers only representative points

Specifications require verification of every I/O point, but integrators sometimes document a sample and extrapolate. Owners and commissioning authorities cross-check the report against the I/O point list and reject the package when terminal units, exhaust fans, or metering points are missing.

PM

Compare the checked point count in the report to the submittal point list. Unaddressed controllers and skipped terminal-level points are the usual gaps.

Program and graphics backups never delivered

The package includes a polished O&M binder but no editable controller program, graphics database, or point database. Without the source files the owner cannot restore a failed controller or expand the system, so reviewers who know to look for the backups reject the package as unusable for long-term operation.

PM

Require the files in the manufacturer's native engineering format on owner-controlled media, and verify they open. PDF screenshots of the graphics are not a backup.

Software licensed to the integrator with admin credentials withheld

Many BAS platforms are licensed and protected by tiered passwords. If the license stays in the integrator's name or the owner receives only view-only access, the owner is locked to one service provider and cannot fully operate or modify what they bought.

PM

Confirm the license certificate names the owner and that administrator-level credentials are transferred in writing as a closeout condition, not left in the integrator's control.

Network and address documentation does not match the live system

BACnet device instances, MS/TP MAC addresses, and IP assignments are frequently changed during startup as controllers are added or re-addressed. An as-built network diagram that reflects the design rather than the field leaves a future integrator unable to find devices on the bus.

PM

Spot-check several device addresses and instance numbers on the diagram against the workstation device list before accepting the network documentation.

Relevant CSI Spec Sections

The MasterFormat specification sections that govern Division 25 Integrated Automation closeout. Pull these from the project spec to confirm exact requirements for your project.

25 00 00
Integrated Automation

The broadscope section establishing general requirements, submittals, and closeout deliverables for the automation system.

25 01 00
Operation and Maintenance of Integrated Automation

Governs the O&M manual content, record documents, and maintenance requirements for the BAS.

25 10 00
Integrated Automation Network Equipment

Covers supervisory controllers, servers, and network hardware; review for what network documentation must be delivered.

25 13 00
Integrated Automation Control and Monitoring Network

The control and monitoring network requirements (BACnet, LON, Modbus); relevant to as-built topology and device addressing.

25 50 00
Integrated Automation Facility Controls

Field and application-specific controllers; review for point lists and checkout requirements.

25 90 00
Integrated Automation Control Sequences

The control sequences section; the as-built sequences of operation must conform to and update this content.

Closeout Checklist: Division 25 Integrated Automation

Use this checklist when collecting documents from your subs and engineer. Print or save as PDF for your project files.

Control Documentation

Network and Software

Licensing and Access

Equipment and O&M

Training and Acceptance

Pro Tips: What Experienced PMs Do Differently

The things that don't appear in the spec but that experienced GC PMs know from hard experience. These are the insights worth sharing.

Schedule BAS closeout collection around commissioning, not the general punch list.

The integrator's as-built sequences, FPT records, and trend data only exist after commissioning is finished. If you wait until the general punch list is closed, the integrator has often demobilized and trend logs may be purged from a temporary server. Capture the program backups and trend exports the week functional testing wraps.

Get the editable program files, not screenshots of the graphics.

A PDF of the graphics looks like documentation but cannot restore a failed controller. The deliverable that matters is the native engineering database (WebCTRL, Metasys, Desigo, Niagara, EcoStruxure, and similar) that lets a future technician re-download logic. Make 'controller and graphics database backup, verified to open' an explicit line item.

Resolve the license and credential transfer before the integrator's final payment.

BAS platforms are licensed software with tiered passwords. Owners who accept view-only access discover at the first expansion that they are locked to one dealer. Tie transfer of the owner-registered license and administrator credentials to the integrator's final pay application.

Reconcile the as-built point list against the TAB and Division 23 closeout.

The BAS set points should match what the TAB contractor balanced to and what the mechanical sequences require. When duct static, minimum outside air, or differential pressure set points in the as-built sequences disagree with the TAB report, reviewers notice. Coordinate Division 25 and Division 23 closeout so the numbers agree.

Frequently Asked Questions

Questions GC PMs and subcontractors ask most often about Division 25 Integrated Automation closeout.

Who provides Division 25 closeout documents: the mechanical contractor or the controls contractor?
Almost all of it comes from the controls contractor or system integrator, who may be a subcontractor to the mechanical contractor or a direct sub to the GC. The mechanical contractor supplies the equipment the BAS controls, but the sequences, point-to-point checkout, network diagrams, and program backups are the integrator's deliverables. Identify the integrator by name early, because they are usually the last trade on site and the hardest to bring back.
Is Division 25 the same as the BAS documentation in Division 23?
They overlap but are not identical. Division 23 controls work that lives within the mechanical scope (instrumentation and control for HVAC) often appears under section 23 0900, while Division 25 covers the integrated, building-wide automation network that ties multiple systems together. On many projects the same integrator produces both, but any document referencing BACnet, LON, Modbus, or enterprise integration across systems belongs in Division 25.
What program backups do we actually need from the integrator?
At minimum the controller logic and program files, the graphics and point database, the alarm and trend configuration, and the firmware and version log, all in the manufacturer's native engineering format. These let a future technician restore a failed controller and modify the system. PDF screenshots of the graphics are useful for reference but are not a usable backup.
Do we need a commissioning report if the project has no commissioning authority?
Not a formal CxA report, but the integrator is still required by most Division 25 specifications to perform start-up, point-to-point checkout, and functional testing and to document them. On commissioned and many energy-code projects (ASHRAE 90.1 and LEED), an independent commissioning authority witnesses functional performance tests and issues a report with an issues log that must be closed before acceptance.
Why does the owner care so much about software licenses and passwords?
Because the BAS is licensed software protected by tiered access. If the license stays in the integrator's name or the owner only receives operator-level access, the owner cannot fully program or expand the system and is effectively locked to one service provider. Confirm the license is registered to the owner and that administrator credentials transfer in writing at closeout.

If you'd rather we handle the entire Division 25 package for you...

Closeout Desk collects, classifies, and organizes all your Division 25 Integrated Automation documentation, plus every other division on the project. We flag what's missing before you submit, so you're not discovering gaps after the owner reviews the package. Fixed-fee pricing. Delivered in 1–10 business days depending on urgency.

$1,500–$3,500 flat fee 1–10 business days No commitment until scope is confirmed All divisions in one package